ONGOING PROJECTS / Kayasehir – Basaksehir Metro Line Rigid Catenary System

Kayasehir – Basaksehir Metro Line Rigid Catenary System
  • Administration: AYGM

    Customer: SENBAY

    Total Line Lenght: 14 km

    Project Manager: 2

    Electrical Engineers: 4

    Technicians: 22

    Machine Operators: 8

    Working Machines: 8

    Pick-up Trucks: 4

    Contract Duration: 720 Days