  • Administration: TCDD
    Main Contractor: DEMULAŞ
    Total Line Length: 32 km

    Personnel Structure:

    • Project Manager: 1

    • Electrical Engineer: 1

    • Technician: 12

    • Machine Operator: 3

    Equipment:

    • Construction Machine: 3

    • Off-Road Vehicle: 2

    Contract Duration: 270 days